If you’re planning a kitchen or bathroom remodel in Chamblee, the permit usually comes from the City of Chamblee’s Planning and Development Department. This guide covers which projects need a permit, what goes into the application, how long review takes and how inspections work, so the permit is part of your plan from the start. It’s based on the city’s own permitting pages, its Permit Required Checklist and its residential inspections guide.
First, Check That Your Address Is in the City
Chamblee’s city limits have grown through annexation, and some nearby land is still outside them. Inside the city, the City of Chamblee issues the permit. In unincorporated DeKalb County, the county’s Permits, Plan Review & Inspections Division reviews plans, issues permits and conducts inspections (DeKalb County, Permits, Plan Review & Inspections). Sexton Woods is partly in Chamblee and partly in Brookhaven (Wikipedia, Chamblee, Georgia); in the Brookhaven part, our Brookhaven permit guide applies. Our Chamblee kitchen budget guide explains how the city limits changed.
When Does a Remodel Need a Permit in Chamblee?
The city’s rule is broad. Its About Permitting page says permits are generally required for all residential and commercial new construction, additions and renovations, and for demolition (interior and building), electrical work, low-voltage wiring, heating and air conditioning, and plumbing (City of Chamblee, About Permitting).
The city’s Permit Required Checklist (dated August 2021) answers the common kitchen and bath questions line by line (City of Chamblee, Permit Required Checklist):
| Your project | Permit? |
|---|---|
| Interior remodel that includes drywall, lighting and/or non-structural framing | Yes |
| New plumbing fixture that requires piping alterations | Yes |
| Bathroom fixture repair or replacement that needs piping alterations | Yes |
| New electrical circuit, or an electrical service upgrade or relocation | Yes |
| Gas piping | Yes |
| Replacing a hard-wired appliance | Yes |
| New doors or windows that require structural alterations | Yes |
| Interior work limited to painting, tiling, carpeting and/or trim | No |
| Bathroom fixture repair or replacement with no piping changes | No |
| Replacing a plug-in appliance | No |
The city’s FAQ points homeowners to that checklist and says it’s preferable to confirm the permit requirements before starting (City of Chamblee, Planning and Development FAQ). A complete kitchen or bathroom renovation, with new wiring, lighting, plumbing and drywall, falls on the “Yes” side.

How to Apply: The iWorq Portal
Chamblee takes permit applications through its iWorq online portal (iWorq, City of Chamblee). For an interior renovation, the city’s page lists:
- A web-form application or the city’s Building Permit application, with the property owner’s signature or an Owner permission affidavit
- A digital PDF of the plans: site plan or survey, elevation plans and floor plans
(City of Chamblee, Interior Renovation)
Contractors must also provide copies of their current State certifications (general, trade or specialty contractor) and their company business license with the application (About Permitting). If the job includes interior demolition, the city’s Interior Demo page lists a demolition application, a site plan or survey and an asbestos survey (City of Chamblee, Interior Demo). Mechanical, electrical and plumbing work each have their own application on the city’s Component Permits page (City of Chamblee, Component Permits).
The Building Permit application also says the permit is void if no construction activity begins within six months of the issue date, unless an extension is granted under the City Code. Questions go to the Planning and Development Department at (770) 986-5010 or chambleedevelopment@chambleega.gov (FAQ).
Who Can Apply, and Who Pulls the Permit
The Building Permit application says only the property owner, architect, general contractor or another authorized agent should sign it as the applicant, and a homeowner acting as the contractor provides a Declaration Form. We pull the permits for our projects, and that’s how we prefer to work.
Plan Review: About 5 Business Days
The city’s FAQ says plan review for residential building permits takes approximately 5 business days for the first submittal, and that review times are estimates that can fluctuate during peak construction seasons. The About Permitting page sets a goal of up to 5 business days for an initial residential submittal and up to 3 business days for each re-submittal. You can check a permit’s status in the iWorq portal with the permit number or the site address (FAQ).
On fees, the FAQ says plan review fees are a flat rate, while building permit fees are calculated from the area of construction. The current amounts are on the city’s permitting fee schedule. Work started without a permit is subject to a Notice of Violation or a Stop Work order from Code Enforcement, usually with extra fees.
Plan the review into your schedule before demolition day. Our step-by-step kitchen remodel guide shows where permits fit.
Inspections, Smoke Detectors and the Certificate
All inspection requests go through the city’s online portal, using the permit number and an access code. For contractors, the code is their license number; for homeowners doing their own work, it’s the street number of the address (City of Chamblee, Schedule an Inspection). The general contractor listed on the permit must schedule all inspections, including those for subcontractors. Homeowners can schedule them only if they’re acting as the general contractor and submitted a homeowner declaration form (FAQ).
The city’s residential inspections guide (May 2025) adds these rules for every project (City of Chamblee, Residential Permit Inspections Reference Guide):
- Request a next-business-day inspection before 4 PM Monday to Thursday, or before 11 AM on Friday. Late or holiday requests go to the second business day. (The city’s FAQ page says 4:00 p.m. for every weekday, so allow for the earlier Friday cutoff.)
- Permits and approved plans must be posted on site.
- Construction hours are 7 AM to 7 PM Monday to Friday and 9 AM to 5 PM on Saturday, with no construction on Sundays or City holidays.
- Smoke detectors must be upgraded.
- The rough inspection is a combination inspection: framing plus all mechanical, electrical and plumbing work at the same time. Final inspections are combined the same way.
- Certificates of Occupancy and Completion must be requested 2 business days after all final inspections are approved.
Chamblee Homes and the Permits They Tend to Need
Many Chamblee neighborhoods date from the 1950s and 1960s. Sexton Woods is a mix of 1950s ranch homes and newer craftsman-style infill, Huntley Hills was established in the early 1960s, and many houses in Beverly Hills/Beverly Woods were built in the early 1950s as housing for workers at the nearby Doraville GM plant (Wikipedia, Chamblee, Georgia). Kitchens in those houses are often small and closed off, so opening a wall is a common goal. That alters the building, and a load-bearing wall is structural work for the drawings. Our guide to taking out a load-bearing wall covers beams and costs, and our guide to split-level kitchens covers stairs and half-levels.
If your home was built before 1978, federal rules require firms that disturb lead-based paint in a renovation to be certified and to follow specific work practices (EPA, Lead Renovation, Repair and Painting Program).

How We Plan a Permitted Remodel
Our showroom at 4353 Tilly Mill Road is about 3 miles from central Chamblee, and we work on homes within about 20 miles of it. We do complete kitchen and bathroom renovations, and our process has four steps:
- Initial meeting at your home, where we talk through your goals and measure the space.
- Showroom visit at our Tilly Mill Road showroom, where you look at materials and finishes and go over the plan.
- Finalizing the design, when every selection and measurement is confirmed and the permit drawings are ready.
- Installation. Your project is backed by our one-year contractor warranty.
See the kitchens we remodel in Chamblee and our bathroom work in Chamblee for the work we do there, or everything we do in Chamblee. Next door, see our Doraville page.
Chamblee Permit FAQ
Do I need a permit to remodel my kitchen in Chamblee?
Usually, yes. The City of Chamblee’s Permit Required Checklist lists an interior remodel that includes drywall, lighting or non-structural framing as needing a permit, along with new electrical circuits, gas piping and new plumbing fixtures that need piping alterations. Work limited to painting, tiling, carpeting or trim doesn’t need one.
Where do I apply for a building permit in Chamblee?
Through the city’s iWorq online portal. For an interior renovation, the city lists the application with the property owner’s signature or an Owner permission affidavit, plus a PDF of the site plan or survey, elevations and floor plans. The Planning and Development Department is at (770) 986-5010.
How long does plan review take in Chamblee?
The city says plan review for residential building permits takes approximately 5 business days for the first submittal, and its goal is up to 3 business days for each re-submittal. The city notes that review times can fluctuate during peak construction seasons.
Who schedules inspections on a Chamblee permit?
The general contractor listed on the permit must schedule all inspections, including those for subcontractors. A homeowner can schedule them only when acting as the general contractor with a homeowner declaration form on file.
Is my home permitted by the City of Chamblee or DeKalb County?
It depends on the address. Inside city limits, the City of Chamblee issues permits. In unincorporated DeKalb County, the county’s Permits, Plan Review & Inspections Division does. Sexton Woods is split between Chamblee and Brookhaven, so check which city your parcel is in.
Plan Your Chamblee Remodel
For other cities, see Dunwoody’s permit rules, how Sandy Springs handles permits and the Buckhead and Atlanta permit guide. For the general rules, read Do I Need a Building Permit for a Kitchen Renovation?