If your kitchen remodel moves plumbing, adds circuits, runs a gas line or takes out a wall, plan on a building permit from the City of Brookhaven. This guide walks through what the city says about when a permit is needed, what an interior alteration application includes, how review works in the city’s Project Portal and who can pull the permit. The permit details below come from the city’s own permit pages, linked in each section, so you can check the current version before you start.
First, Check That Your Address Is in the City of Brookhaven
Brookhaven became a city on December 17, 2012, after a referendum that July made it DeKalb County’s 11th city (Wikipedia). The city’s Building Permits page says any construction or redevelopment project requires a permit from the City of Brookhaven, and that building permitting is housed under its Community Development Department. One local catch: Wikipedia also notes that a majority of the Historic Brookhaven neighborhood around Capital City Country Club lies inside the City of Atlanta. If that’s your street, Atlanta’s process applies, and our guide to permits in Buckhead and the City of Atlanta covers it. The city’s Building Permits page also links to an Address Verification tool if you’re not sure which side of the line you’re on.
When Does a Kitchen Remodel Need a Permit in Brookhaven?
The city’s Building Permits page answers this directly: a permit must be obtained before beginning construction, erection, alteration or repair to a building or structure, or to its mechanical, gas, plumbing, electrical or energy conservation systems, other than ordinary repairs. Permits for emergency work must be obtained within 24 hours after the work starts. The page points to Sec. 7-118 of the city’s Code of Ordinances for exemptions.
In a kitchen, those systems come up quickly. Here is how common kitchen work lines up with the systems the city lists. The city makes the final call on your project:
- Moving the sink or dishwasher: plumbing.
- New outlets, circuits or lighting: electrical.
- A gas range or cooktop in a new spot: gas.
- A new vented range hood: mechanical (ventilation).
- Opening or removing a wall: the building structure. Our post on taking out a load-bearing wall in a Brookhaven ranch covers that case in detail.
If your project sits on the line between a repair and an alteration, ask the city before you start. The Building Permits page sends permit questions to the Permitting Team, code questions to the Building Official and plan review questions to the Building Plan Reviewer.
What an Interior Alteration Application Includes
A kitchen remodel inside an existing house falls under the city’s Interior Alterations for Residential Construction permit. The city lists these requirements:
- Construction drawings drawn to scale, showing existing conditions and the proposed changes
- Structural drawings, if applicable
- Stamped drawings for engineered building components
- An Authorized Agent Form
- A Contractor Registration Form, if applicable
The city’s Comprehensive Building Permit Checklist adds two details for residential interior alterations: every room must be labeled as to its use, and the drawings must include an electrical schematic. For a kitchen, that means the plans show the room as it is today and as it will be, with the electrical layout drawn out.
How Plan Review Works in the Project Portal
Applications and plans go through the city’s Project Portal, which the Building Permits page says is also used to make payments, schedule inspections and track project status. The checklist lays out the path:
- Application: the application and required plans are submitted through the Project Portal.
- Plan review: plans are reviewed by all applicable departments.
- Comments, if needed: if the plans don’t meet current codes or more information is required, a comment letter and redlined plans are posted to the portal and the applicant is notified by email.
- Resubmittal: revised plans and the initialed comment letter are uploaded to the portal.
- Plans approved: approved plans are electronically stamped and the applicant is notified by email.
- Fees paid: by credit card through the portal, or by check or credit card in person at City Hall.
- Permit issued: the permit and approved plans are released through the portal to the contractor of record or their authorized agent.
On timing, the city’s FAQ says only this: after allowing 10 business days for review, if you haven’t received review comments or approval, contact a permit tech to check the status. Comments and resubmittals add their own rounds, so build the permit into your schedule rather than counting on a date.
Who Can Pull a Permit in Brookhaven?
Generally, a licensed Georgia contractor. The city’s FAQ says it enforces Georgia state contractor licensing laws and that contractors must provide their state licenses to pull permits. The exceptions it names are a homeowner doing work on their own home who provides a notarized Homeowner Affidavit, and some limited specialty trades. The Building Permits page links to the Georgia Secretary of State’s contractor license verification, so you can look up any contractor’s license before you sign.
We pull the permits for our projects, and that’s how we prefer to work. Our Georgia license number is RBC0006934.
What a Brookhaven Permit Costs
The city doesn’t publish a flat price for a kitchen. Its FAQ says permit fees, including minimum fees and review fees, are listed in the City’s Fee Schedule, and that valuation is calculated using the most recent version of the ICC Data Valuation table. Check the current Fee Schedule linked from the Building Permits page for the numbers, or ask the Permitting Team, which the city lists as the contact for fee questions. For what the whole kitchen costs, see what a Brookhaven kitchen remodel costs by house type.
Older Homes: Asbestos and Lead-Based Paint
Major residential development took place in Brookhaven from the 1950s to the 1970s, and the area was largely built out by 1980 (Wikipedia). The city’s Building Permits page includes Asbestos and Lead-Based Paint among its quick links. If your house dates from that era, read those pages before demolition starts.
Planning the Rest of the Kitchen
The permit follows the design, so most of the decisions come first. If you’re choosing counters, our guide to edge profiles and slab thickness covers one choice that shows up on the drawings, and our comparison of quartz, quartzite and granite helps you pick the material first. For the full picture of how we work in the city, see our Brookhaven kitchen remodeling page or the Brookhaven services hub. Nearby, homeowners can read our Sandy Springs permit guide or our Dunwoody permit guide. Next door in Chamblee, see the Chamblee guide.
How We Run a Kitchen Remodel
- Initial Meeting: We meet at your home to talk through your goals and budget and take measurements. At the end of the visit we schedule your showroom appointment.
- Showroom Visit: You compare door, color, countertop and hardware samples, then review the detailed design with 3D color renderings and an itemized proposal.
- Finalizing Design: Our designer and master craftsman do a final design review and final measure at your home.
- Installation: Our remodeling team carries out the build.
Our work is backed by a one-year contractor warranty. You can see the full scope of what we do on our kitchen remodeling services page.
Frequently Asked Questions
Do I need a permit to remodel my kitchen in Brookhaven?
Usually, if the work goes beyond ordinary repairs. The City of Brookhaven requires a permit before construction, alteration or repair to a building or to its mechanical, gas, plumbing, electrical or energy conservation systems, other than ordinary repairs. Sec. 7-118 of the city code lists the exemptions.
What does Brookhaven require for an interior alteration permit?
Construction drawings to scale showing existing conditions and proposed changes, structural drawings if applicable, stamped drawings for engineered components, an Authorized Agent Form and, if applicable, a Contractor Registration Form. The city checklist also asks for rooms labeled by use and an electrical schematic.
Can a homeowner pull a building permit in Brookhaven?
Yes, in one case the city names: a homeowner doing work on their own home who provides a notarized Homeowner Affidavit. Otherwise the city generally requires a licensed Georgia contractor to pull the permit.
How much does a Brookhaven building permit cost?
The city lists permit, minimum and review fees in its Fee Schedule, and it calculates valuation with the most recent version of the ICC Data Valuation table. Check the current Fee Schedule on the city website for amounts.
How long does Brookhaven permit review take?
The city does not promise a review time. Its FAQ says that if you have not received comments or approval after allowing 10 business days for review, you should contact a permit tech to check the status.
Do you pull permits for kitchen remodels in Brookhaven?
Yes. We pull the permits for our projects, and that is how we prefer to work. Our Georgia contractor license number is RBC0006934.
Talk to Us About Your Kitchen
Thinking about a Brookhaven kitchen? Call (404) 997-3788 or book a free consultation. We start at your home, and the quote is free.
Kitchen Design Studio & Remodeling of Atlanta
4353 Tilly Mill Road #150
Atlanta, GA 30360
Phone: (404) 997-3788
Office hours: Monday-Thursday 8:30 a.m.-4:30 p.m., Friday 8:30 a.m.-3 p.m., closed Saturday and Sunday.
Licensed in Georgia: RBC0006934